INSTALLATIONSVEJLEDNING
26 trin til en færdig Fritstående motoriseret pergola.
Fritstående aluminiumspergola med motoriseret lameltag — seks omkredsstørrelser (3×3 → 4×6) fra én fælles 26-trinsprocedure.
-
01
Forbered hjørneforbindelses-sæt
Pre-build the four corner connection sets — set projection vs width orientation now.
RAMME12 min -
02
Byg den forreste U-ramme
Insert the front C-1 gutter into B-1/B-2 pillars to form the front U-frame on the ground.
RAMME18 min -
03
Byg den bageste U-ramme
Repeat for the rear C-2 gutter into A-1/A-2 pillars — keep both U-frames square.
RAMME18 min -
04
Løft de U-formede rammer
Lift both U-frames simultaneously — two installers per frame, mind the powder coating.
RAMME25 min -
05
Monter venstre sideprofil D-1
Install the left D-1 side perimeter profile between the two U-frames.
RAMME18 min -
06
Monter højre sideprofil D-2
Install the right D-2 side perimeter profile — frame is now closed.
RAMME18 min -
07
Kontrollér diagonaler og drænpropper
Verify diagonals match the size table (3×3: 386 · 3×4: 466 · 3×5: 554.5 · 4×4: 527.5 · 4×5: 602.4 · 4×6: 683.7 cm) and seat drainage plugs.
RAMME15 min -
08
Monter F-tagrender i fremspringsretning
Mount F gutters in the projection direction.
RAMME18 min -
09
Monter E-tagrender i breddesretning
Mount E gutters in the width direction — perimeter complete.
RAMME18 min -
10
Fastgør toptagrender oppefra
Fix all top gutters from above with 3.9 mm screws.
RAMME15 min -
11
Forsegl gummisamlinger
Seal rubber junctions at all gutter intersections — neutral silicone bead.
RAMME12 min -
12
Forbered standardlameller
Pre-cut and prepare the standard PN-LM-500 lamellas to width.
LAMELLER20 min -
13
Forbered motorlamellen
Prepare the dedicated PN-LM-501 motor blade — drive coupling on motor side.
LAMELLER15 min -
14
Monter motoren på D-1-profilen
Mount the PN-MT-500 motor on the D-1 profile per code map orientation.
LAMELLER25 min -
15
Monter motorlamellen
Install the motor blade onto the rotation pin first — verifies free movement.
LAMELLER20 min -
16
Justér motorarmen
Adjust the motor arm angle so the motor blade closes flush.
LAMELLER18 min -
17
Monter de resterende lameller
Insert the remaining standard lamellas one by one — verify rotation by hand.
LAMELLER30 min -
18
Monter bevægelsesarme
Install the PN-AR-500 movement arms linking all blades to the motor blade.
LAMELLER25 min -
19
Monter bevægelsesarm-dæksler
Cap with the PN-CV-500 movement-arm cover profiles.
LAMELLER15 min -
20
Monter søjledæksler
Mount the PN-DZ-510 pillar covers (4 corners).
AFSLUTNING12 min -
21
Monter bageste afslutningsprofil
Install the PN-CV-501 rear cover profile.
AFSLUTNING12 min -
22
Monter forreste afslutningsprofil
Install the PN-CV-502 front cover profile.
AFSLUTNING12 min -
23
Monter hjørnedæksler
Install the corner cover trims at the four upper corners.
AFSLUTNING15 min -
24
Træk motorkabler
Route the motor cables down through the designated pillar channel.
AFSLUTNING15 min -
25
Monter LED-strip og PVC-dæksel
Install the LED strip into the gutter recess and snap on the PVC cover.
AFSLUTNING18 min -
26
Færdiggør elinstallation
Complete electrical wiring at the controller — verify motor direction and end-stops.
AFSLUTNING30 min
Om denne fritstående motoriseret pergola-installationsvejledning
Luxa Aperio 500 — Fritstående motoriseret pergola · LuxaShade aluminium roof family. 26 steps · 2 installers · Edition 2026.1.
EN AW-6063 T6 alloy · QUALICOAT class 2 powder coating · EN 1991-1-4 wind-load rated · RTS-compatible motor wiring on motorised variants.
Hvorfor følge den officielle PONARC × LuxaShade-procedure
- EN 1991-1-4 · QUALICOAT class 2 · EN AW-6063 T6
- RTS-compatible motor wiring (motorised variants)
- Gutter slope 1.5% · drainage inside columns
- Edition 2026.1 · Januar 2026 · DA